According to an audit conducted this summer, the project is expected to exceed its original budget by more than $25 million, or 18 percent.
PwC Consulting, a business of PricewaterhouseCoopers LLP, released the audit report to School of Medicine Dean Jeffrey Houpt on July15.
When the project was proposed in 1995, officials filed a certificate of need -- an estimate of total cost -- for $140.2 million. The final projection estimates a budget of $165.6 million, the report states.
Construction of the hospitals is also behind schedule. Initially, officials planned a November 1999 opening. But the second and final phase will not be done until February 2003, officials say. Phase one ended in February 2002.
The report outlines five areas that comprised most of the cost overrun: construction, consultation, equipment, financing and the contingency.
Construction and consultation both cost more than expected because of a multitude of unforeseen charges.
Financing cost overruns resulted because UNC Hospitals pursued a larger bond purchase than originally planned and because of unforeseen capital interest expenses from the building delay. But the audit states, "these interest expenses would have been paid by the Hospital in any event."
Though equipment costs were actually more than $100,000 less than projected, PwC cited the area because the cost documentation for equipment expenditures was "incomplete and decentralized."
But Karen McCall, vice president of public affairs for UNC Hospitals, contested this assertion, saying the project did have an equipment budget.